Porch replaced, 5/19-6/??/2015
5/15/2015 - First delivery of Porch materials (soffit) were filthy
5/19/2015 - Porch start, but materials delivered were filthy, so workers advised to reorder
5/20/2015 - Porch restart with clean materials, left unfinished
5/21-25/2015 - No Work Done, still waiting on materials
5/26/2015 - No Work Done, Dumpster removed
5/26/2015-06/17/2015 - No Work Done
6/18/2015 - Final Porch Parts Delivered: Pillars, Caps, Bases
6/19/2015 - Tree trimming and first Porch Pillars installed
6/20/2015 - Porch Progress
6/21/2015 - Porch Progress
6/22/2015 - Porch Progress